
Your Columbus City Utilities is preparing Columbus for
tomorrow. Thanks to your support, we have been busy improving the City’s
wastewater collection and treatment system. Much has been done, more is underway
and there’s still more to do.
Columbus was one of the first Indiana communities to have state officials
approve a plan corrects long-standing combined sewer overflow conditions and
protects the environment. Our innovative plan eliminates overflows of untreated
wastes into local rivers and streams for all but the worst rainstorm events. To
make that plan work, we have constructed on a large diameter sewer, a storm
pretreatment and pumping center and an 18 million gallon storage facility to
hold the peak flow until it can be returned for treatment. Each of these
projects will retain and create jobs, protect our environment and prepare
Columbus for the future.
Other completed projects eliminate untreated overflows and correct some long
standing capacity issues on the south and east side. These projects will help
prevent sewer backups for many Columbus residents.
Replacing the old, unreliable, outdated treatment plant later this year is an
important part of the sewer system improvement plan. Our current facility is 55
years old and it frequently experiences costly mechanical breakdowns and creates
odor problems in our community.
The new facility will enable us to compete for jobs, protect the environment
and will be more reliable and more energy efficient. It will also be more
effective in the treatment of waste and provide odor control. The design for the
state-of the-art new plant is completed and is under regulatory review. Funding
for the project will use low interest loans from a state program and a rate
adjustment for you and other customers. In an effort to reduce costs, we are
also watching progress on the proposed Federal Stimulus package. We will seek
approval of our financing plan in April and or May of this year and construction
will start soon after.
Keeping the jobs that we have, competing for new jobs, protecting the
environment and using tax dollars wisely---these are all of the benefits of the
sewer improvement projects. Check out the Columbus Tomorrow projects we have
underway:
View Larger Map
|
Designed By:
|
Strand Engineers
|
|
Constructed By:
|
Atlas Excavating
|
|
Final Contract Amount:
|
$ 1,796,320.01
|
All the storm flows of the combined district come together on the west side of
Water Street in the south section of downtown Columbus. Atlas Construction of
West Lafayette, Indiana was chosen to construct the nearly 2,000 feet of 108”
diameter sewer that will direct these peak flows away from the old overflows and
to the large pump station and basins. The project is complete and operational
during storm events.
View the Water Street Sewer Project Photo Gallery
|
Designed By:
|
Strand Engineers
|
|
Constructed By:
|
Shook Construction
|
|
Final Contract Amount:
|
$10,333,985.34
|
All
combined storm flows are then directed to this new pumping screening and
disinfection facility. Located at the east end of the Water Street, sewer this
facility is capable of pumping wastewater at a rate of 240 million gallons per
day. Four large travelling trash screens prevent large items in the flow from
damaging equipment and creating odors in the holding basins. Liquid Chlorine is
added a precautionary disinfectant and a potential odor concerns are controlled
through an odor control system. Shook Construction of Indianapolis was awarded
the contract to build this facility in 2007 and it is now complete.
View the Haw Creek Headworks Project Photo Gallery
|
Designed By:
|
Strand Engineers
|
|
Constructed By:
|
Sunesis Contractors
|
|
Final Contract Amount:
|
$6,175,754.00
|
Several years ago Mariah Foods changed its meat packing operations and no longer
needed three large basins they had used for waste pretreatment in its
slaughterhouse days. Realizing the impending need for storm water storage the
CCU purchased these facilities on a ten year contract. By re-utilizing this
piece of property the CCU also saved considerable funds by converting these
basins into storm-holding basins rather than building a completely new facility.
Still, there was a great deal of work involved in transforming these earthen
holding ponds into an eighteen million gallons holding facility. Higher
sidewalls, concrete floor and vinyl slope walls are only some of the
improvements that were made. Mixers have been installed to prevent the stored
waters from becoming septic (due to oxygen depletion) and creating objectionable
odors. The basin is designed to contain the runoff from a 10yr frequency storm
event and return that for treatment within three days of capture. When that
storm intensity is exceeded (like earlier this year) the system will capture the
“first flush” of the combined sewers (thought to contain the most contaminants)
and will screen and disinfect flows even after the basin is full as it overflows
to the Haw Creek. Sunesis Contractors of Cincinnati was chosen in 2007 to
complete this work. This project has now been completed and is operational.
View the Mariah Basins Project Photo Gallery
|
Designed By:
|
Strand Engineers
|
|
Constructed By:
|
S.J. Louis Construction
|
|
Final Contract Amount:
|
$ 3,926,984.52
|
The
final component of the combined sewer correction program involved the
construction of a 66” diameter sewer from Water Street to 15th Street along the
west side of the downtown to carry flows from the final uncorrected point of
combined sewer overflow to the new holding facility. Constructing a 66”
pipeline, at grade, though existing underground utilities, beneath five sets of
railroad tracks, under three highways and though one very busy city park
provided a unique set of challenges in design and construction. S.J. Louis of
Minnesota won the contract in mid 2008 and their tunneling division completed
the major road and railroad crossings in November. The work was completed in the
spring of 2009.
View the Noblitt Sewer Project Photo Gallery
|
Designed By:
|
GRW Engineers
|
|
Constructed By:
|
TEAM Contracting
|
|
Final Contract Amount:
|
$1,736,648.00
|
Homes in the eastern residential subdivisions have
experienced sewer backups occasionally, due to infiltration and limited capacity
of the trunk sewer serving this area. This project seeks to relieve the capacity
constraints through the construction of over 16,000 feet of relief sewer. The
CCU is also taking the opportunity to install 10,000 feet of water main to
reinforce the supply for this area. TEAM contracting of Indianapolis has
completed approximately 90% of this work. The second part of the department’s
program to eliminate flooding problems on the eastside is to minimize the
infiltration of ground water into the sewers. To this end the CCU contracted
with Bowen Engineering and Insituform Inc. to install a cured in place plastic
liner (CIPP) within a portion of the older cracked and leaking clay pipe. The
work was completed as an energy efficiency project and under those statutory
guidelines using the justification that keeping unpolluted waters from entering
the system prevented unnecessary pumping and treatment. Over 10,000 lineal feet
of sewer was rehabilitated and leaky lateral connections were repaired to 114
homes.
View the Eastside Water & Sewer Project Photo Gallery
|
Designed By:
|
GRW Engineers
|
|
Constructed By:
|
TEAM Contracting
|
|
Final Contract Amount:
|
$1,312,914.59
|
Located on the east end of Indiana Avenue this sewage
pump station serves an area south of Tenth Street and east of Mapleton, plus the
former Eastern Bartholomew Regional Sewer District as well as properties east of
Taylor and South of 25th.
Besides being taxed during rainfalls the old station had suffered
catastrophic failure in 2008. The
new pump station is complete and connected to the Eastside Sewer (above).
|
Designed By:
|
Strand Engineers
|
|
Constructed By:
|
Atlas Excavating
|
|
Final Contract Amount:
|
$4,800,000
|
The Southside Lift Station is and was located on CR
150 W about 1 mile south of CR 200S.
Capacity and age had made the previous station a liability.
Repetitious ruptures in the station’s force main created unsafe
conditions for residents and motorists on SR 11 in Garden City.
The project consists of a new sewage pump station with increased capacity
and more reliability and a new sewage force main along a new route that will
coordinate the transition from our current wastewater facility to the new one
under construction.
|
Designed By:
|
Strand Engineers, CH2MHill
Engineers, Christopher Burke Engineering
|
|
Constructed By:
|
Bowen Engineering
|
|
Final Contract Amount:
|
$ 42,848,240.00
|
A key component of the wastewater improvement program is the replacement of the City’s aging, outdated and unreliable wastewater treatment plant. In 2007, the Utility Service Board chose a design team to head up this work consisting of engineers from Strand, CH2MHill and Christopher Burke Engineers. This team conducted research, along with the CCU staff, and a basic technology for treatment was chosen early in 2008. Throughout the remainder of the year the design team has addressed the myriad of details involved in designing a project of this scope.
In the spring of 2009 financing was arranged and bids were sought for the project. Bowen Engineering was awarded the contract in June and construction is in progress with completion expected in 2011.
The project is being funded through low interest loans from the State Revolving Fund and grants from the American Reinvestment and Recovery Act and the SRF Sustainability program.
|